MEGHALAYA LEGISLATIVE ASSEMBLY

BUDGET SESSION

STARRED

QUESTIONS AND ANSWERS

Monday, the 24th March, 2003

Shopping Complex

Shri ARDHENDU CHAUDHURI
 
 

Shri F. LYNGDOH  (Minister in-charge, Urban Affairs)

*6. Will the Minister in-charge, Urban Affairs be pleased to state:-

   
(a) Approximate time for completion of the Shopping Complex at Old Civil Hospital, Police Bazar, Shillong?   (a) Sir, the schedule time for completion of the project is 13th July, 2003.
(b) Whether the Government has drawn up any allotment of shops and premises including mode proposed therein to be adopted?   (b) Sir, the policy for allotment is being prepared.
(c) Total number of shops which will be available for the public after the completion of the project?   (c) Sir, 78 nos. of shops are under construction.